A Complete Success of Roof Lifting for the Second 150,000m3 Cryogenic Concrete Full Capacity Tank of Zhejiang Jiahua Energy undertaken by YPDI A Complete Success of Roof Lifting for the Second 150,000m3 Cryogenic Concrete Full Capacity Tank of Zhejiang Jiahua Energy undertaken by YPDI Jun. 23, 2021
A Complete Success of Roof Lifting for the Second 150,000m3 Cryogenic Concrete Full Capacity Tank of Zhejiang Jiahua Energy undertaken by YPDI The whole lifting process took only 2 hours and 48 minutes, the lifting speed was stable and the progress was smooth. It took only 6 months from the start of the concrete pouring of the caps on December 21, 2020 to the completion of this air-lifting. Learn More